What is the difference between NS 8405 and NS 8406?

What is the difference between NS 8405 and NS 8406?

A number of standards have been developed for construction contracts, including NS 8405 and NS 8406. Below, we will look at the main differences between these two standards.

When are standards used?

All standards (NS) are used in agreements between businesses.

Agreements between businesses and consumers are largely regulated by law through the Housing Construction Act, which includes standard forms created by, among others, the Consumer Council.

When are the NS 8405 and NS 8406 standardsused?

Both of these apply to agreements between contractors and builders, where the contractor undertakes to construct a building based on drawings and descriptions, etc., prepared by the builder.

This is described as the builder having design responsibility, in contrast to a turnkey contract where NS 8407 is used.

What is the difference?

It is contained in the notification rules and the consequences of failure to notify. NS 8405 sets strict formal requirements, while NS 8406 has less formal deadlines.

When should notification be given?

The client may demand (require) that changes to the agreement be made, in which case the contractor may be obliged to carry out the changes. The contractor must give notice if the required changes mean that he believes he is entitled to increased remuneration or needs more time.

The contractor must similarly notify the client if something is discovered that results in additional work that he could not have foreseen when the contract was entered into, and which he believes justifies increased remuneration or time.

Consequences of failure to notify

If the individual does not give notice in accordance with the rules, the other party may reject such claims:

  • NS 8405 response deadline: Anyone who receives a change notification must respond without undue delay, which is interpreted as within a few days.
  • NS 8406 response deadline: Anyone who receives a change notification must respond within a reasonable time, which means that you have a little more time.

Requirements for notifications and changes

NS 8405 and NS 8406 require that this be done in writing, and if the parties have agreed, this may be done by email.

Changes and notices recorded in construction meeting minutes are considered to be in writing.

When should each standard be used?

This should be considered on a case-by-case basis, and according to what the parties deem most appropriate.

It is therefore important to consider other agreements in the construction project and the need for organization and coordination between multiple contractors.

If the builder has several contractors, the same agreement should be used for all of them, so that there is no risk of missing anything. This can happen if one contractor notifies the builder in accordance with 8405, and the builder must then notify another contractor in accordance with 8406. A late response from the second contractor may mean that you are bound by the terms of the first contractor.

Furthermore, NS 8405 should be used if the client has subcontractors but has a turnkey contract agreement with the main contractor, cf. NS 8407.